Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Gayatri Projects LTD | 20021207 | Ameremaon water supply scheme | 487.77 | 314.68 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 31 | 31 | Yes | 0 | NA | No | 28202.00 | 26745.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Karaundikala | Amaremaoo | 441380 | Amaremaoo | 448 | 448 | 100 | Har Gar Jal | Not Certified | 
| 2 | Sultanpur | Karaundikala | Amaremaoo | 441381 | Junedpur | 62 | 34 | 55 | Work In Progress | Not Certified | 
| 3 | Sultanpur | Karaundikala | Amaremaoo | 441382 | Daudpur | 21 | 21 | 100 | Har Gar Jal | Not Certified |