Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20021590 | CHAMPAPUR & KHANKUIYA NANKAR WSS | 346.06 | 158.05 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 10388.00 | 10388.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Barhni | Champapur | 446402 | Champapur | 184 | 175 | 95 | Work In Progress | Not Certified |
| 2 | Siddharth Nagar | Barhni | Khadkuiya Nankar | 446409 | Khankuiya Nankar | 342 | 341 | 100 | Work In Progress | Not Certified |
| 3 | Siddharth Nagar | Barhni | Champapur | 446815 | Thusuri | 48 | 45 | 94 | Work In Progress | Not Certified |