Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Megha | 20021732 | Gaurahi buzurg | 192.76 | 140.82 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 17 | 17 | Yes | 0 | NA | No | 8749.00 | 8749.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Domariyaganj | Gaurahi Bujurg | 448471 | Goorahi Buzurg | 312 | 312 | 100 | Har Gar Jal | Not Certified | 
| 2 | Siddharth Nagar | Domariyaganj | Gaurahi Bujurg | 448475 | Suhalwa | 70 | 70 | 100 | Har Gar Jal | Not Certified | 
| 3 | Siddharth Nagar | Domariyaganj | Gaurahi Bujurg | 448478 | Surji | 74 | 74 | 100 | Har Gar Jal | Not Certified | 
| 4 | Siddharth Nagar | Domariyaganj | Gaurahi Bujurg | 655783 | Gaurahi Khurd | 184 | 184 | 100 | Har Gar Jal | Not Certified |