Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Lucknow | NCC Ltd. | 20022036 | Hatauli &Ghusauli | 287.04 | 202.43 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Lucknow | Malihabad | Ghusauli | 415476 | Ghusauli | 293 | 293 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Lucknow | Malihabad | Hatauli | 415477 | Jagdishpur Khurd | 64 | 64 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Lucknow | Malihabad | Hatauli | 415478 | Hatauli | 195 | 195 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 11290.00 | 11290.00 |