Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | VSA | 20022149 | MAWAI KALA & MAWAI KHURD & BHAGIPUR WSS | 546.73 | 330.81 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Milkipur | BHAGI PUR | 436623 | BHAGI PUR | 243 | 243 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Milkipur | MAWAI KHURD | 436624 | MAWAI KHURD | 275 | 275 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Milkipur | MAWAI KALA | 436625 | MAWAI KALA | 268 | 268 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 3461.00 | 30072.00 |