Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | VSA | 20022152 | DEHRIYAWAN & MAURAWA WSS | 378.95 | 236.24 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Bikapur | MAHURAWAN | 437245 | HARIHAR PUR | 37 | 37 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Bikapur | Dehriyawan | 437246 | Balli Pur | 69 | 69 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Bikapur | Dehriyawan | 437247 | Dehriyawan | 134 | 134 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ayodhya | Bikapur | Dehriyawan | 437248 | Nabha Pur | 20 | 20 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Ayodhya | Bikapur | MAHURAWAN | 437249 | MAWRAVA | 151 | 151 | 100 | Har Gar Jal | Not Certified | Not Verified |
6 | Ayodhya | Bikapur | Dehriyawan | 437255 | Vishnoher Pur | 78 | 78 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 2607.00 | 16369.00 |