Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | VSA | 20022218 | BACHHRAM PUR & CHAWARDHAR WSS | 605.01 | 312.37 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Bikapur | Chawardhar | 437174 | Tiwari Ka Purwa | 78 | 78 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Bikapur | Chawardhar | 437175 | Sresar | 111 | 111 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Bikapur | Chawardhar | 437238 | CHWARDAAR | 151 | 151 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ayodhya | Bikapur | Bachram Pur | 437239 | Bachram Pur | 260 | 260 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Ayodhya | Bikapur | Bachram Pur | 437240 | Khema Saray | 156 | 156 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 4344.00 | 3430.00 |