Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20023495 | Saujana Jhaya WSS | 261.10 | 161.98 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bulandshahr | Jahangirabad | Sojna Jhaya | 393644 | Sojna Jhaya | 404 | 404 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Bulandshahr | Jahangirabad | Sojna Jhaya | 393645 | Pirpur | 66 | 66 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 22 | 22 | Yes | 0 | NA | No | 7792.00 | 7520.00 |