Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Chandauli | GA INFRA - BABA (JV) | 20023548 | Kawalpura_Sonhuli WS | 396.67 | 221.27 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Chandauli | Dhanapur | Kawal Pura | 474320 | Kawal Pura | 171 | 171 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Chandauli | Dhanapur | Sonhuli | 474330 | Sonhuli | 393 | 389 | 99 | Work In Progress | Not Certified | Not Verified |
3 | Chandauli | Dhanapur | Sonhuli | 658470 | Sonhuli Gangbarar | 4 | 4 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 23195.00 | 21370.00 |