Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sant Ravidas Nagar | Welspun Kaveri Infraprojects JV | 20023573 | Dalupur Multi Village Water Supply Scheme | 372.18 | 225.92 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | No | 0 | NA | No | 13317.00 | 12654.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Ravidas Nagar | Bhadohi | DALAPUR | 477071 | DALAPUR | 391 | 391 | 100 | Har Gar Jal | Not Certified | 
| 2 | Sant Ravidas Nagar | Bhadohi | Garulpur | 477072 | Mansinghpur | 110 | 110 | 100 | Har Gar Jal | Not Certified | 
| 3 | Sant Ravidas Nagar | Bhadohi | Garulpur | 477073 | Garulpur | 132 | 132 | 100 | Har Gar Jal | Not Certified | 
| 4 | Sant Ravidas Nagar | Bhadohi | Mamhar | 477133 | Mamhar | 211 | 207 | 98 | Work In Progress | Not Certified | 
| 5 | Sant Ravidas Nagar | Bhadohi | Mamhar | 477134 | Bhairopur | 45 | 45 | 100 | Har Gar Jal | Not Certified | 
| 6 | Sant Ravidas Nagar | Bhadohi | Mamhar | 477135 | Jiyanpur | 60 | 60 | 100 | Har Gar Jal | Not Certified |