Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Etawah | Indian Hume Pipe | 20023845 | Bidhipur PWS | 211.89 | 155.66 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 10798.00 | 10634.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Mahewa | Bidhipur | 420080 | Ekari | 196 | 196 | 100 | Har Gar Jal | Not Certified | 
| 2 | Etawah | Mahewa | Bidhipur | 420081 | Bidhipur | 186 | 185 | 99 | Work In Progress | Not Certified | 
| 3 | Etawah | Mahewa | Bidhipur | 420082 | Basaiya Har | 120 | 120 | 100 | Har Gar Jal | Not Certified |