Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Balrampur | Larsen & Toubro Ltd | 20025430 | Piraila Mafi-Hashim Para Water Supply Scheme | 335.82 | 217.82 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Balrampur | Gaindas Buzurg | Piraila Mafi | 444350 | Piraila Mafi | 193 | 193 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Balrampur | Gaindas Buzurg | Piraila Mafi | 444351 | Dumaria | 109 | 109 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Balrampur | Gaindas Buzurg | Hasim Para | 444361 | Hasim Para | 159 | 159 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 25 | 25 | Yes | 0 | NA | No | 11621.00 | 11621.00 |