Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Jaunpur | AFCONS | 20026108 | Raipur Water Supply Scheme | 290.44 | 172.99 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Jaunpur | Mahrajganj | Raiepur | 469003 | Keshopur | 59 | 59 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Jaunpur | Mahrajganj | Raiepur | 469004 | Manjhanpur | 77 | 77 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Jaunpur | Mahrajganj | Raiepur | 469005 | Rajepur | 64 | 64 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Jaunpur | Mahrajganj | Raiepur | 469006 | Raipur | 102 | 102 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 12 | Yes | 0 | NA | No | 21298.00 | 19241.00 |