Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | VSA | 20029964 | Arjanepur W/S Scheme | 218.56 | 141.74 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 | 14 | Yes | 0 | NA | No | 3512.00 | 3154.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Mohammadabad | Arjanepur | 473468 | Arjanepur | 180 | 156 | 87 | Work In Progress | Not Certified |
| 2 | Ghazipur | Mohammadabad | Arjanepur | 473469 | Baikunthpur | 8 | 8 | 100 | Har Gar Jal | Not Certified |
| 3 | Ghazipur | Mohammadabad | Arjanepur | 473470 | Umarpur | 127 | 127 | 100 | Har Gar Jal | Not Certified |