Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Basti | VSA | 20032207 | RAGHUNATHPUR,SALEMPUR KUNWAR GP WSS | 278.32 | 210.61 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Basti | Paras Rampur | Raghunathpur | 449090 | Raghunathpur | 176 | 176 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Basti | Paras Rampur | Salempur Kunwar | 449091 | Paltijot | 22 | 22 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Basti | Paras Rampur | Raghunathpur | 449092 | Gholava | 20 | 20 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Basti | Paras Rampur | Salempur Kunwar | 449093 | Ashokpur | 20 | 20 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Basti | Paras Rampur | Salempur Kunwar | 449102 | Salempur Kunawar | 140 | 140 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 13518.00 | 13518.00 |