Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Power Mech Projects Ltd | 20032427 | Badgau Gram Panchayat Water Supply Scheme | 293.55 | 166.77 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Kalakankar | Bargaun | 429322 | Bargaun | 378 | 376 | 99 | Work In Progress | Not Certified | Not Verified |
2 | Pratapgarh | Kalakankar | Bargaun | 429323 | Fattehullapur | 51 | 51 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Pratapgarh | Kalakankar | Bargaun | 429324 | Baharamaee | 70 | 70 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 19555.00 | 19000.00 |