Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Basti | VSA | 20032812 | ACHRAUL&KARI GAHNA GP WSS | 310.88 | 200.26 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Basti | Paras Rampur | Kari Gahna | 449199 | Narainpur Pandey | 31 | 31 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Basti | Paras Rampur | Kari Gahna | 449200 | Kari Gahna | 132 | 132 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Basti | Paras Rampur | Kari Gahna | 449201 | Hadahi | 73 | 73 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Basti | Paras Rampur | Achraul | 449304 | ACHARAUL | 0 | 0 | 0 | Work In Progress | Not Certified | Not Verified |
5 | Basti | Paras Rampur | Achraul | 449310 | Marwatiya | 313 | 313 | 100 | Har Gar Jal | Certified | Not Verified |
6 | Basti | Paras Rampur | Achraul | 449311 | Khamariya | 239 | 239 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 10362.00 | 10362.00 |