Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mau | LC INFRA | 20032906 | SULTANIPUR GRAM PANCHAYAT RURAL WATER SUPPLY SCHEME | 268.95 | 145.78 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mau | Ranipur | Sultanipur | 466199 | Sultanipur | 166 | 166 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Mau | Ranipur | Sultanipur | 466200 | Hirapur | 77 | 77 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Mau | Ranipur | Sultanipur | 466201 | Bibipur Mu,sultanipur | 42 | 42 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Mau | Ranipur | Sultanipur | 466202 | Nizampur Mu, Sultanipur | 69 | 69 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Mau | Ranipur | Sultanipur | 466203 | Yerdeva Mu Sultanipur | 15 | 15 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 18 | 18 | Yes | 0 | NA | No | 14843.00 | 15000.00 |