Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GA INFRA - BABA (JV) | 20033286 | ekdangi sarwanpur WATER SUPPLY SCHEME | 191.08 | 113.99 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 6409.00 | 6000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Koilsa | EKDANGI SARWANPUR | 461238 | JAFARAMAU | 140 | 135 | 96 | Work In Progress | Not Certified |
| 2 | Azamgarh | Koilsa | EKDANGI SARWANPUR | 461239 | EKDANGI | 135 | 132 | 98 | Work In Progress | Not Certified |
| 3 | Azamgarh | Koilsa | EKDANGI SARWANPUR | 461240 | SARWANPUR | 88 | 87 | 99 | Work In Progress | Not Certified |