Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20033828 | SAHNE MAU water Supply Scheme | 534.74 | 402.41 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 27292.00 | 26930.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Akbarpur | Sanjarpur | 439062 | Sanjarpur | 327 | 327 | 100 | Har Gar Jal | Not Certified |
| 2 | Ambedkar Nagar | Akbarpur | Sahne Mau | 439063 | Koinda | 112 | 105 | 94 | Work In Progress | Not Certified |
| 3 | Ambedkar Nagar | Akbarpur | Sahne Mau | 439064 | MUSTFABAD GANGILA | 65 | 62 | 95 | Work In Progress | Not Certified |
| 4 | Ambedkar Nagar | Akbarpur | Sahne Mau | 439065 | Sahne Mau | 174 | 171 | 98 | Work In Progress | Not Certified |