Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sant Ravidas Nagar | Welspun Kaveri Infraprojects JV | 20036678 | Kandhiya Multi GP water supply shcheme | 500.89 | 182.32 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 44 | 44 | No | 0 | NA | No | 20761.00 | 19861.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Ravidas Nagar | Bhadohi | Kandhiya | 477005 | Kandhiya | 251 | 251 | 100 | Har Gar Jal | Not Certified | 
| 2 | Sant Ravidas Nagar | Bhadohi | Lachhapur | 477006 | Jolhapur | 60 | 58 | 97 | Work In Progress | Not Certified | 
| 3 | Sant Ravidas Nagar | Bhadohi | Lachhapur | 477007 | Lachhapur | 145 | 144 | 99 | Work In Progress | Not Certified | 
| 4 | Sant Ravidas Nagar | Bhadohi | Kandhiya | 477008 | Gondamir Imamali | 1 | 1 | 100 | Har Gar Jal | Not Certified | 
| 5 | Sant Ravidas Nagar | Bhadohi | Hari Chandanpur | 477206 | Hari Chandanpur | 75 | 75 | 100 | Har Gar Jal | Not Certified | 
| 6 | Sant Ravidas Nagar | Bhadohi | Hari Chandanpur | 477207 | Amawa Kala | 368 | 367 | 100 | Work In Progress | Not Certified |