Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20047645 | BALRAMPUR Water Supply Scheme | 457.80 | 405.20 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 30297.00 | 27544.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Tanda | Basantpur | 437528 | Basantpur | 97 | 95 | 98 | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Tanda | Basantpur | 437530 | Gobraha | 8 | 8 | 100 | Har Gar Jal | Not Certified |
| 3 | Ambedkar Nagar | Tanda | Basantpur | 437531 | Goa Makrandpur | 46 | 41 | 89 | Work In Progress | Not Certified |
| 4 | Ambedkar Nagar | Tanda | Basantpur | 437532 | Saidwara | 24 | 23 | 96 | Work In Progress | Not Certified |
| 5 | Ambedkar Nagar | Tanda | Balrampur | 437533 | Balrampur | 284 | 284 | 100 | Har Gar Jal | Not Certified |
| 6 | Ambedkar Nagar | Tanda | Balrampur | 437534 | YADAVPUR | 69 | 68 | 99 | Work In Progress | Not Certified |