Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pilibhit | VISHVARAJ | 20051086 | KANJA NATH +2 MULTI GP WATER SUPPLY SCHEME | 414.64 | 275.06 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pilibhit | Lalaurikhera | Gauneri Badi | 404812 | Gauneri Badi | 378 | 378 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Pilibhit | Lalaurikhera | Gauneri Dan | 404821 | Gauneri Dan | 272 | 272 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Pilibhit | Lalaurikhera | Kanjanath Patti | 404822 | Kanja Nath Patti | 238 | 238 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 12240.00 | 11943.00 |