Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20051953 | AUSANPUR & DHARIYAMAOO WATER SUPPLY SCHEME | 379.34 | 254.12 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 32176.00 | 32459.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Lambhua | Ausanpur | 440888 | Ausanpur | 157 | 150 | 96 | Work In Progress | Not Certified |
| 2 | Sultanpur | Lambhua | Ausanpur | 440889 | Bharkat | 30 | 29 | 97 | Work In Progress | Not Certified |
| 3 | Sultanpur | Lambhua | Dhariyamaoo | 440900 | Dhariyamaoo | 170 | 154 | 91 | Work In Progress | Not Certified |
| 4 | Sultanpur | Lambhua | Dhariyamaoo | 440901 | Bhagiyapur | 31 | 31 | 100 | Har Gar Jal | Not Certified |
| 5 | Sultanpur | Lambhua | Dhariyamaoo | 440902 | Daswatpur | 34 | 34 | 100 | Har Gar Jal | Not Certified |
| 6 | Sultanpur | Lambhua | Dhariyamaoo | 440903 | Madhupur | 8 | 1 | 12 | Work In Progress | Not Certified |
| 7 | Sultanpur | Lambhua | Dhariyamaoo | 440904 | Gangapur | 65 | 48 | 74 | Work In Progress | Not Certified |