Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Pratapgarh Power Mech Projects Ltd 20052118 Bidhasin Gram Panchayat Water Supply Scheme 231.00 121.91 Verified Verified view more

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Pratapgarh Babaganj Bidhasin 429057 Bidhasin 213 185 87 Work In Progress Not Certified Not Verified
2 Pratapgarh Babaganj Bidhasin 429058 Purepir Gulam 74 74 100 Har Gar Jal Not Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 1 20 20 Yes 0 NA No 11320.00 10960.00