Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20052612 | KHUNTI BUZURG JJM SCHEME | 283.86 | 189.18 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 12117.00 | 12000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Pasgawan | Khunti Buzurg | 408834 | Khunti Buzurg | 342 | 342 | 100 | Har Gar Jal | Not Certified | 
| 2 | Lakhimpur Kheri | Pasgawan | Khunti Buzurg | 408835 | Nadauwa | 129 | 126 | 98 | Work In Progress | Not Certified | 
| 3 | Lakhimpur Kheri | Pasgawan | Khunti Buzurg | 408836 | Raipur | 69 | 65 | 94 | Work In Progress | Not Certified | 
| 4 | Lakhimpur Kheri | Pasgawan | Khunti Buzurg | 408837 | Choupadiya | 2 | 2 | 100 | Har Gar Jal | Not Certified |