Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Power Mech Projects Ltd | 20052945 | Miranpur & Rajapur Mufharid Multiple Gram Panchayat Water Supply Scheme | 415.65 | 140.54 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Baba Belkharnath Dham | Miranpur | 430206 | Miranpur | 174 | 167 | 96 | Work In Progress | Not Certified | Not Verified |
2 | Pratapgarh | Baba Belkharnath Dham | Miranpur | 430207 | Rampur Kurmiyan | 125 | 125 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Pratapgarh | Baba Belkharnath Dham | Miranpur | 430208 | Hardattapur | 46 | 30 | 65 | Work In Progress | Not Certified | Not Verified |
4 | Pratapgarh | Baba Belkharnath Dham | Rampur Mufarid | 430217 | Rampur Mufarid | 175 | 175 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 39 | 39 | Yes | 0 | NA | No | 23377.00 | 22960.00 |