Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Power Mech Projects Ltd | 20053018 | Kalyanpur & Purefhattesingh Multiple Gram Panchayat Water Supply Scheme | 356.18 | 129.68 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Rampur Sangramgarh | Pure Fattesingh | 428956 | Pure Fattesingh | 108 | 106 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Pratapgarh | Rampur Sangramgarh | Pure Fattesingh | 428958 | Pure Gangaram | 39 | 38 | 97 | Work In Progress | Not Certified | Not Verified |
3 | Pratapgarh | Rampur Sangramgarh | Pure Fattesingh | 428960 | Purewan | 16 | 15 | 94 | Work In Progress | Not Certified | Not Verified |
4 | Pratapgarh | Rampur Sangramgarh | Kalyanpur | 428961 | Kalyanpur | 304 | 283 | 93 | Work In Progress | Not Certified | Not Verified |
5 | Pratapgarh | Rampur Sangramgarh | Kalyanpur | 428962 | Pure Hiranand | 30 | 30 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 22038.00 | 21540.00 |