Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20054825 | PEMAPUR WATER SUPPLY SCHEME | 347.68 | 155.17 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | NA | 0 | NA | No | 23808.00 | 23843.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Jaisinghpur | Pemapur | 440679 | Hasrampur | 52 | 48 | 92 | Work In Progress | Not Certified |
| 2 | Sultanpur | Jaisinghpur | Pemapur | 440680 | Domanpur | 21 | 18 | 86 | Work In Progress | Not Certified |
| 3 | Sultanpur | Jaisinghpur | Pemapur | 440681 | Pemapur | 225 | 219 | 97 | Work In Progress | Not Certified |
| 4 | Sultanpur | Jaisinghpur | Pemapur | 440682 | Khajuri | 188 | 180 | 96 | Work In Progress | Not Certified |