Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20055702 | GOPINATHPUR & BARUAA UTTARI WATER SUPPLY SCHEME | 450.60 | 281.94 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 36840.00 | 36840.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Lambhua | Gopinathpur | 440985 | Gopinathpur | 279 | 275 | 99 | Work In Progress | Not Certified |
| 2 | Sultanpur | Lambhua | Baruaa Uttari | 440986 | Baruaa Uttari | 263 | 260 | 99 | Work In Progress | Not Certified |
| 3 | Sultanpur | Lambhua | Baruaa Uttari | 440987 | Murarchak | 119 | 109 | 92 | Work In Progress | Not Certified |
| 4 | Sultanpur | Lambhua | Baruaa Uttari | 440988 | Tazanpur | 12 | 7 | 58 | Work In Progress | Not Certified |
| 5 | Sultanpur | Lambhua | Baruaa Uttari | 440989 | Barapur | 21 | 18 | 86 | Work In Progress | Not Certified |