Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20055743 | MALWA & PAHARPUR SARI BHEEKAM WATER SUPPLY SCHEME | 449.82 | 276.82 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 32775.00 | 40155.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Motigarpur | Paharpur Sarai Bheekam | 441592 | Paharpur Saraibheekam | 346 | 346 | 100 | Har Gar Jal | Not Certified | 
| 2 | Sultanpur | Motigarpur | Malwa | 441595 | Malwa | 194 | 194 | 100 | Har Gar Jal | Not Certified | 
| 3 | Sultanpur | Motigarpur | Malwa | 441596 | Karaundi | 165 | 165 | 100 | Har Gar Jal | Not Certified |