Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Larsen & Toubro Ltd | 20057185 | Iguwa Urf Kathgawan Multi Village Water Supply Scheme | 444.98 | 287.45 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | BHAGWATPUR | IGUWA URF KATHGAWAN | 431607 | IGUWA URF KATHGAWAN | 764 | 762 | 100 | Work In Progress | Not Certified | Not Verified |
2 | Prayagraj | BHAGWATPUR | IGUWA URF KATHGAWAN | 431608 | MOHIUDDINPUR AMRAIN | 59 | 52 | 88 | Work In Progress | Not Certified | Not Verified |
3 | Prayagraj | BHAGWATPUR | IGUWA URF KATHGAWAN | 431609 | CHANDRSAIN | 208 | 204 | 98 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 29277.00 | 29277.00 |