Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20057221 | GOPALPUR RAYEPUR AND GOPALPUR MAGHAAYA WATER SUPPLY SCHEME | 294.65 | 189.89 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 20 | Yes | 0 | NA | No | 19138.00 | 15356.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Lambhua | Gopalpur Maghaaya | 441009 | Gopalpur Maghaaya | 181 | 170 | 94 | Work In Progress | Not Certified |
| 2 | Sultanpur | Lambhua | Gopalpur Rayepur | 441010 | Gopalpur Rayepur | 131 | 127 | 97 | Work In Progress | Not Certified |
| 3 | Sultanpur | Lambhua | Gopalpur Rayepur | 441011 | Kunwarpur N0 3 | 63 | 51 | 81 | Work In Progress | Not Certified |