Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20058209 | NIJAMPUR (GOGP) JJM | 542.63 | 327.96 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 23612.00 | 20762.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | BAWAN | JAGDISHPUR | 412369 | JAGDISHPUR | 260 | 260 | 100 | Har Gar Jal | Not Certified |
| 2 | Hardoi | BAWAN | NIJAMPUR | 412377 | NIJAMPUR | 240 | 240 | 100 | Har Gar Jal | Not Certified |
| 3 | Hardoi | BAWAN | NIJAMPUR | 412378 | SABIRPUR | 149 | 149 | 100 | Har Gar Jal | Not Certified |
| 4 | Hardoi | BAWAN | TERIA | 412461 | UDAIPUR | 180 | 180 | 100 | Har Gar Jal | Not Certified |
| 5 | Hardoi | BAWAN | TERIA | 412462 | TERIA | 318 | 318 | 100 | Har Gar Jal | Not Certified |