Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | UNIVERSAL MEP | 20058505 | Bikawal & Tanda Sufi WSS | 427.58 | 274.83 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Rudauli | Tanda Sufi | 436426 | Tanda Sufi | 181 | 181 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Rudauli | Tanda Sufi | 436427 | Bhadawal | 165 | 165 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Rudauli | Bikawal | 436431 | Bikawal | 240 | 240 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ayodhya | Rudauli | Bikawal | 436432 | Newajpur | 76 | 76 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 16029.00 | 16029.00 |