Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Fatehpur | Gayatri Projects LTD | 20058708 | DAMAPUR & MUCHWAPUR | 406.76 | 256.98 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Fatehpur | Teliyani | Damapur | 427752 | Damapur | 237 | 237 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Fatehpur | Teliyani | Damapur | 427753 | Bairampur | 104 | 104 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Fatehpur | Teliyani | Damapur | 427754 | Alanapur | 86 | 86 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Fatehpur | Teliyani | Muchuwapur | 427781 | Muchuwapur | 197 | 197 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Fatehpur | Teliyani | Muchuwapur | 427782 | Kakaberi | 138 | 138 | 100 | Har Gar Jal | Certified | Not Verified |
6 | Fatehpur | Teliyani | Muchuwapur | 427783 | Mardanpur | 39 | 39 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 15110.00 | 15112.00 |