Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20058740 | SAIDPUR RASEEDPUR WSS | 386.30 | 286.73 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 27 | 27 | Yes | 0 | NA | No | 21141.00 | 21141.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Ramnagar | Saidpur Raseedpur | 437967 | Saidpur Raseedpur | 119 | 119 | 100 | Har Gar Jal | Certified |
| 2 | Ambedkar Nagar | Ramnagar | Saidpur Raseedpur | 437968 | Junaidpur | 147 | 147 | 100 | Har Gar Jal | Certified |
| 3 | Ambedkar Nagar | Ramnagar | Saidpur Raseedpur | 437969 | Hafizpur Langri | 253 | 253 | 100 | Har Gar Jal | Certified |
| 4 | Ambedkar Nagar | Ramnagar | Saidpur Raseedpur | 437970 | Alapur | 32 | 32 | 100 | Har Gar Jal | Certified |