Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | NCC Ltd. | 20058754 | PASINGAVAN (GOGP) JJM | 545.50 | 316.85 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | Shahabad | Miyanpur | 411909 | Miyanpur | 217 | 212 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Hardoi | Shahabad | Pasigavan | 411910 | Pasigavan | 241 | 241 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Hardoi | Shahabad | Miyanpur | 411911 | Husainapur Dhaukal | 115 | 112 | 97 | Work In Progress | Not Certified | Not Verified |
4 | Hardoi | Shahabad | Mithnapur | 411913 | Mithnapur | 276 | 275 | 100 | Work In Progress | Not Certified | Not Verified |
5 | Hardoi | Shahabad | Mithnapur | 411914 | JHARSAALAMPUR | 183 | 183 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 24945.00 | 23945.00 |