Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | UNIVERSAL MEP | 20058802 | BHELSAR & KHAIRANPUR WSS | 1167.74 | 548.03 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Rudauli | Khairanpur | 436374 | Jahanpur | 74 | 74 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Rudauli | Khairanpur | 436375 | Khairan Pur | 321 | 321 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Rudauli | Khairanpur | 436376 | Lakhnipur | 117 | 102 | 87 | Work In Progress | Not Certified | Not Verified |
4 | Ayodhya | Rudauli | Khairanpur | 436377 | Jasmand | 160 | 148 | 92 | Work In Progress | Not Certified | Not Verified |
5 | Ayodhya | Rudauli | Bhelsa R | 436378 | Bhelsar | 1117 | 1117 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 2 | 1 | 1 | 63 | 63 | Yes | 0 | NA | No | 47138.00 | 44434.00 |