Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20058973 | Patiyapar and Dhangarwa GP WSS | 264.53 | 125.30 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 9048.00 | 9048.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Khuniyaon | Dhangadhawa | 448238 | Majhegada | 59 | 59 | 100 | Har Gar Jal | Not Certified |
| 2 | Siddharth Nagar | Khuniyaon | Dhangadhawa | 448239 | Dhangarwa | 175 | 175 | 100 | Har Gar Jal | Not Certified |
| 3 | Siddharth Nagar | Khuniyaon | Patiya Par | 448241 | Patiyapar | 148 | 148 | 100 | Har Gar Jal | Not Certified |