Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Basti | VSA | 20059077 | NATHPUR PANDEY, BILARI BHITI GP wss | 298.59 | 189.74 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Basti | Paras Rampur | Nathpur Pandey | 449106 | Nathpur Pandey | 248 | 248 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Basti | Paras Rampur | Bilari Bhiti | 449184 | Gaura Gosain | 67 | 67 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Basti | Paras Rampur | Bilari Bhiti | 449185 | Bilari Bhiti | 87 | 87 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 11643.00 | 10643.00 |