Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | JMC - Lakshmi (JV) | 20059305 | Pilkhanari urf Sabitgarh & Jatola & Habibpur WSS | 442.26 | 161.13 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 19162.00 | 16500.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Araniya | Pilkhanhari Urf Sabitgarh | 394164 | Pilkhanhari Urf Sabitgarh | 460 | 455 | 99 | Work In Progress | Not Certified | 
| 2 | Bulandshahr | Araniya | Gangavali | 394167 | Habibpur | 146 | 128 | 88 | Work In Progress | Not Certified | 
| 3 | Bulandshahr | Araniya | Jatola | 394168 | Jatola | 320 | 314 | 98 | Work In Progress | Not Certified |