Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bahraich | PNC-SPML-JV | 20059426 | GOKULPUR NAWABGANJ MVS PWS | 168.27 | 105.35 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bahraich | Nawabganj | Gokulpur | 441781 | Shivrampur Telyani | 27 | 27 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Bahraich | Nawabganj | Gokulpur | 441782 | Khusalipurwa | 98 | 98 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Bahraich | Nawabganj | Gokulpur | 441783 | Gokul Pur | 139 | 139 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 25 | NA | No | 10721.00 | 10721.00 |