Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | VSA | 20059764 | BALIBHADARPUR GOVARAHA AND MAU NANKAR WSS | 263.62 | 150.97 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | Khuniyaon | Mau Nankar | 448393 | Mau Nankar | 191 | 176 | 92 | Work In Progress | Not Certified | Not Verified |
2 | Siddharth Nagar | Khuniyaon | Balibhadra Pur Urf Gobaraha | 448394 | Balibhadra Pur Gobaraha | 107 | 94 | 88 | Work In Progress | Not Certified | Not Verified |
3 | Siddharth Nagar | Khuniyaon | Balibhadra Pur Urf Gobaraha | 448396 | Rajwapur Urf Belwa | 26 | 26 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 10475.00 | 10475.00 |