Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Etawah | OMIL-JWIL (JV) | 20059995 | Baisoli Sadikpur PWS | 235.26 | 161.75 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 11723.00 | 11550.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Bharthana | Baisoli Sadikpur | 419926 | Baisoli Bhanpur | 324 | 294 | 91 | Work In Progress | Not Certified |
| 2 | Etawah | Bharthana | Baisoli Sadikpur | 419927 | Sadikpur | 61 | 56 | 92 | Work In Progress | Not Certified |