Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20060133 | Bodah WSS | 215.51 | 94.46 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 6352.00 | 5520.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Sikandrabad | Bodah | 393165 | Shahwazpur | 22 | 15 | 68 | Work In Progress | Not Certified |
| 2 | Bulandshahr | Sikandrabad | Bodah | 393166 | Bodah | 275 | 274 | 100 | Work In Progress | Not Certified |
| 3 | Bulandshahr | Sikandrabad | Bodah | 393167 | ASAFPUR | 22 | 0 | 0 | Work In Progress | Not Certified |