Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20060377 | sukhatia jaskaranpur gp water supply scheme | 373.87 | 196.73 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 22 | 22 | Yes | 0 | NA | No | 10990.00 | 10768.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bisalpur | Sukatia Jaskaranpur | 405182 | Sukatia Jaskaranpur | 721 | 721 | 100 | Har Gar Jal | Certified |
| 2 | Pilibhit | Bisalpur | Sukatia Jaskaranpur | 405183 | Bhogapur | 184 | 184 | 100 | Har Gar Jal | Certified |
| 3 | Pilibhit | Bisalpur | Sukatia Jaskaranpur | 405184 | Niwa Dandi | 155 | 155 | 100 | Har Gar Jal | Certified |