Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20060382 | SHIBHUAA + 1 MULTI GP WATER SUPPLY SCHEME | 358.60 | 214.91 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 28959.00 | 28759.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bilsanda | Kuraiya Kalan | 404993 | Kuraiya Kalan | 64 | 60 | 94 | Work In Progress | Not Certified | 
| 2 | Pilibhit | Bilsanda | Kuraiya Kalan | 404994 | Kuraiya Khurd | 32 | 27 | 84 | Work In Progress | Not Certified | 
| 3 | Pilibhit | Bilsanda | Kuraiya Kalan | 404995 | Isapur | 83 | 80 | 96 | Work In Progress | Not Certified | 
| 4 | Pilibhit | Bilsanda | Kuraiya Kalan | 404996 | Makrandpur Naka | 97 | 79 | 81 | Work In Progress | Not Certified | 
| 5 | Pilibhit | Bilsanda | Kuraiya Kalan | 404997 | Tulapur | 77 | 72 | 94 | Work In Progress | Not Certified | 
| 6 | Pilibhit | Bilsanda | Shibhuaa | 405111 | Sinbua | 206 | 194 | 94 | Work In Progress | Not Certified |