Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | NCC Ltd. | 20060398 | PITHNAPUR NAGRIA (GOGP) JJM | 451.10 | 248.24 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | Harpalpur | PITHNAPUR NAGARIYA | 412518 | PITHNAPUR | 223 | 210 | 94 | Work In Progress | Not Certified | Not Verified |
2 | Hardoi | Harpalpur | PITHNAPUR NAGARIYA | 412519 | NAGRIYA SADHAU | 115 | 114 | 99 | Work In Progress | Not Certified | Not Verified |
3 | Hardoi | Harpalpur | PITHNAPUR NAGARIYA | 412520 | HARAIYA | 65 | 63 | 97 | Work In Progress | Not Certified | Not Verified |
4 | Hardoi | Harpalpur | PITHNAPUR NAGARIYA | 412521 | MUTHAULI | 6 | 6 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Hardoi | Harpalpur | Mahsulapur | 412535 | Mahsulapur | 358 | 358 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 35 | 35 | Yes | 0 | NA | No | 22360.00 | 22154.00 |