| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20060829 | FATEPUR KHURD + 1 MULTI GP WATER SUPPLY SCHEME | 424.29 | 257.72 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 8 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 45919.00 | 45519.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Puranpur | Haripur Kalan | 405530 | Haripur Kalan | 118 | 95 | 81 | Work In Progress | Not Certified | 
| 2 | Pilibhit | Puranpur | Haripur Kalan | 405531 | Navadia Nadi Kinara Jukna | 85 | 78 | 92 | Work In Progress | Not Certified | 
| 3 | Pilibhit | Puranpur | Haripur Kalan | 405532 | Sundarpur | 41 | 41 | 100 | Har Gar Jal | Not Certified | 
| 4 | Pilibhit | Puranpur | Haripur Kalan | 405533 | Mahewa | 25 | 14 | 56 | Work In Progress | Not Certified | 
| 5 | Pilibhit | Puranpur | Haripur Kalan | 405534 | Haripur Udaipur | 8 | 2 | 25 | Work In Progress | Not Certified | 
| 6 | Pilibhit | Puranpur | Fatepur Khurd | 405657 | Fatepur Khurd | 176 | 168 | 95 | Work In Progress | Not Certified | 
| 7 | Pilibhit | Puranpur | Fatepur Khurd | 405658 | Gatihar | 70 | 50 | 71 | Work In Progress | Not Certified | 
| 8 | Pilibhit | Puranpur | Fatepur Khurd | 405659 | Singhpur T. Chandpur | 73 | 72 | 99 | Work In Progress | Not Certified |